Waste Water Treatment Works Upgrade – Still bay

Hessequa Municipality

ArrowBack to projects

The scope of work comprises New Infrastructure at  the existing Waste Water Treatment Works (WWTW) at Still Bay. It includes upgrades to the existing infrastructure, including a new clarifier and a new screw pump station.

Project Overview

Client:

Hessequa Municipality

Date of Project:

Completed: June 2020

Value:

R7,036,577.66

Consultants:

Neil Lyners and Associates (Pty) Ltd
SAFETY CONSULTANTS: Safe Working Practice