Section 1A:
NHLS Lab & OPD
2.5 Months
Section 1B:
Extensions to New Ward, Extensions to Theatre Block, Extension to EMS Unit
5.5 Working Months
Section 2:
Renovations to New Male Ward, Extensions to Staff Restroom, Extensions to Radiology, Renovations to Outbuilding Linen Bank, External Extensions to Kitchen.
4 Working Months
Section 3:
Renovate Theatres & Complete Theatre additions, Renovations to CSSD,
Renovations to Kitchen
4 Working Months
Section 4A:
Renovate part of Female & Maternity Wards, Renovate Radiology
3 Working Months
Section 4B:
Renovate Main Entrance, Waiting Area & Reception
5 Working Months
Section 5:
Renovate remaining part of Female & Maternity Wards, Renovate new Pediatric
Ward
3.5 Working Months
Department of Health South Africa
Started: October 2019
R11,451,134.52